Project plans, schedules, documents, and updates, together in one place.
School update · November 19, 2026
Next steps: removal of two portable buildings
Asbestos abatement
November 23–December 10, 2026
Demolition
December 11–16, 2026
This work is for the removal of two portable buildings and has a separate schedule from the full PACEUP project described below. The abatement dates above update the schedule in the original district notice dated November 18.
The district notice identifies Room 24, restrooms and kitchen; Rooms 22 and 23; and the roof. It states that certified workers will perform asbestos abatement, work areas will be isolated and posted with signs, and containment, cleaning, and air-monitoring procedures will be used.
The new LAUSD notice describes removal of two portable buildings (Rooms 22, 23, and 24) as part of PACEUP. Preparation and dismantling are scheduled for November 23–December 10. Oversized vehicles are scheduled to remove the building components from campus December 11–16, 2026, according to this notice.
Work hours listed in the notice
November 23–25, 2026
7 a.m.–2:30 p.m.
November 30–December 16, 2026
2:30–9 p.m.
Dates and schedules are subject to change due to unforeseen circumstances.
Schedule note: the earlier school update identified a tentative demolition window of December 11–17. This district notice lists component removal for December 11–16.
Potential impacts
Increased dust during removal activities.
Elevated noise from equipment used to dismantle the buildings.
Temporary traffic congestion on Gleneden Street as large vehicles enter and leave campus.
Measures described by LAUSD
Maintain residents’ access to their driveways.
Provide traffic control during building removal.
Monitor air quality and implement dust mitigation measures.
Fence off all work areas; require workers to wear high-visibility vests and identification badges.
PACEUP is Allesandro’s Playground and Campus Exterior Upgrade Project. LAUSD’s April 2026 bulletin summarizes the March 18 community meeting and describes the planned improvements.
Project scope
Paint the exterior of existing buildings and structures.
Replace approximately 47,000 square feet of paving in the main and kindergarten playgrounds.
Upgrade hardscape, including solar-reflective coating on playgrounds.
Replace playground equipment as necessary.
Add improvements to meet the District’s goal for schoolyards to be 30% green/natural. These may include playfields with irrigation, outdoor learning and activity stations, landscaping, and planting areas.
Install privacy fencing as required.
Upgrade infrastructure, including sanitary sewer and storm drainage utilities, as necessary.
Complete improvements needed for accessibility and local, state, and federal compliance, including ADA, DSA, CEQA, and DTSC requirements.
Anticipated full-project timeline
As listed in LAUSD’s April 2026 bulletin. These are anticipated dates, subject to change; they are separate from the portable-building work in 2026.
Construction start
Fourth quarter of 2027 (October–December)
Projected completion
Fourth quarter of 2029 (October–December)
Project budget
$9 million
View the original project phases diagram
Definition and development; design and environmental studies; approvals; bid and award; construction. Original planning diagram, not a report of current progress.
Site plan
Design concept provided for the project. Final design may change. Select the image to open it.